| Date/Time | Event | Description |
|
| 1/1/2024 |
EFFECTIVE DATE/ STATUTORY DEADLINE |
GRR Effective date 1/1/2024. |
| 1/1/2024 |
EFFECTIVE DATE/ STATUTORY DEADLINE |
|
| 1/1/2024 |
EFFECTIVE DATE/ STATUTORY DEADLINE |
|
| 1/1/2024 |
EFFECTIVE DATE/ STATUTORY DEADLINE |
|
| 1/1/2024 |
EFFECTIVE DATE/ STATUTORY DEADLINE |
|
| 1/1/2024 |
EFFECTIVE DATE/ STATUTORY DEADLINE |
|
| 12/18/2023 |
FINAL ORDER DUE DATE |
5th Partial Stip-Target Order Date |
| 12/18/2023 |
FINAL ORDER DUE DATE |
GRR Commission Order (target) |
| 12/17/2023 |
EXPIRATION DATE |
|
| 12/6/2023 3:00:00 PM |
COMMENTS/RESPONSES DUE |
Parites repsonse to 7th bench request due by 3pm. |
| 11/30/2023 3:00:00 PM |
COMMENTS/RESPONSES DUE |
PGE response 7th Bench Request due by 3pm |
| 11/17/2023 3:00:00 PM |
COMMENTS/RESPONSES DUE |
5th Partial Stip-AWEC’s Reply to 5th partial Stip due by 3pm. |
| 11/15/2023 3:00:00 PM |
COMMENTS/RESPONSES DUE |
PGE's responses to bench request 5-8 are due with November 15 MONET updates. |
| 11/9/2023 3:00:00 PM |
COMMENTS/RESPONSES DUE |
Fifth partial stipulation-Stipulating parties response due by 3pm. |
| 11/8/2023 3:00:00 PM |
COMMENTS/RESPONSES DUE |
Fifth partial stipulation Deadline to request further process due by 3pm |
| 11/7/2023 3:00:00 PM |
COMMENTS/RESPONSES DUE |
PGE's responses to bench request 5-8 are due with the company's November 7 MONET update. |
| 10/24/2023 3:00:00 PM |
COMMENTS/RESPONSES DUE |
Parties responses to Bench Request 5-1 through 5-7, and 5-9 due by 3pm. |
| 10/23/2023 3:00:00 PM |
COMMENTS/RESPONSES DUE |
Parties response to Bench Reqeust #4 due by 3pm. |
| 10/20/2023 3:00:00 PM |
COMMENTS/RESPONSES DUE |
PGE responses to bench requests 5-1 through 5-7, and 5-9 due by 3pm. |
| 10/20/2023 3:00:00 PM |
COMMENTS/RESPONSES DUE |
Parties repsonse to 3rd bench request due by 3pm. |
| 10/18/2023 3:00:00 PM |
COMMENTS/RESPONSES DUE |
PGE's response due for Bench Reqeust #4 due by 3pm. |
| 10/16/2023 3:00:00 PM |
COMMENTS/RESPONSES DUE |
Parties response to SBUA case certification request and proposed budget due |
| 10/16/2023 3:00:00 PM |
COMMENTS/RESPONSES DUE |
Company repsonse to 3rd bench request due by 3pm. |
| 10/11/2023 3:00:00 PM |
STIPULATION DUE |
Stipulation due or status updated due by 3pm. |
| 9/15/2023 3:00:00 PM |
ISSUE STATEMENT DUE |
GRR Issues Lists and Position Statements (all parties) due by 3pm. |
| 9/11/2023 3:00:00 PM |
TESTIMONY/EXHIBITS DUE |
GRR Company Surrebuttal Testimony due by 3pm. |
| 9/11/2023 3:00:00 PM |
BRIEF DUE |
APCU Staff and Intervenor Reply Briefs due by 3pm. |
| 9/8/2023 3:00:00 PM |
TESTIMONY/EXHIBITS DUE |
AWEC's Supplemental Rebuttal Testimony due by 3pm. |
| 8/28/2023 3:00:00 PM |
BRIEF DUE |
APCU Company Opening Brief due by 3pm |
| 8/23/2023 3:00:00 PM |
STIPULATION DUE |
Partial stipulations and supporting testimony due by 3pm. |
| 8/23/2023 3:00:00 PM |
TESTIMONY/EXHIBITS DUE |
Outstanding partial stipulations and supporting testimony due by 3pm. |
| 8/22/2023 3:00:00 PM |
TESTIMONY/EXHIBITS DUE |
GRR Staff and Intervenor Rebuttal Testimony due by 3pm. |
| 8/14/2023 3:00:00 PM |
CROSS EXAMINATION STATEMENT DUE |
Cross-Examination Statements due by 3:00 pm |
| 8/14/2023 3:00:00 PM |
TESTIMONY/EXHIBITS DUE |
Cross-Examination Testimony and Exhibits due by 3pm |
| 8/14/2023 3:00:00 PM |
CROSS EXAMINATION STATEMENT DUE |
APCU Cross-Examination Statements due by 3pm. |
| 8/10/2023 3:00:00 PM |
TESTIMONY/EXHIBITS DUE |
APCU Company Surrebuttal Testimony due by 3pm. |
| 8/1/2023 |
SETTLEMENT CONFERENCE |
GRR Settlement Conference specifics TBD. |
| 7/21/2023 3:00:00 PM |
TESTIMONY/EXHIBITS DUE |
GRR Company Reply Testimony due by 3pm. |
| 7/21/2023 3:00:00 PM |
TESTIMONY/EXHIBITS DUE |
APCU Staff and Intervenor Rebuttal Testimony due by 3pm |
| 6/28/2023 |
SETTLEMENT CONFERENCE |
GRR Staff led Settlement Conference specifics TBD. |
| 6/21/2023 3:00:00 PM |
TESTIMONY/EXHIBITS DUE |
APCU Company Reply Testimony due by 3pm. |
| 6/14/2023 |
SETTLEMENT CONFERENCE |
APCU Settlement Conference specifics TBD. |
| 6/13/2023 3:00:00 PM |
TESTIMONY/EXHIBITS DUE |
GRR Staff and Intervenor Opening Testimony due by 3pm. |
| 6/6/2023 3:00:00 PM |
COMMENTS/RESPONSES DUE |
Parties may submit replies to PGE's responses |
| 5/30/2023 3:00:00 PM |
COMMENTS/RESPONSES DUE |
PGE to Submit Filing Responding to 5/23/23 ALJ Memorandum |
| 5/24/2023 3:00:00 PM |
TESTIMONY/EXHIBITS DUE |
APCU Staff and Intervenor Opening Testimony due by 3pm. |
| 5/3/2023 6:00:00 PM |
PUBLIC COMMENT HEARING |
Notice of Public Comment Hearing. Copies served to service list on 4/14/23. |
| | Location: ZOOM WEBINAR |
| 4/28/2023 |
MISCELLANEOUS |
Intervenor Funding - Justice Case Funding - Target date for Commission Decisions regarding case certification |
| 4/21/2023 |
SETTLEMENT CONFERENCE |
GRR Settlement Conference specifics TBD. |
| 4/18/2023 3:00:00 PM |
COMMENTS/RESPONSES DUE |
Parties response to bench request due by 3 pm. |
| 4/14/2023 |
STAFF WORKSHOP |
APCU Staff Workshop specifics TBD. |
| 4/13/2023 3:00:00 PM |
STAFF WORKSHOP |
GRR Staff Workshop specifics TDB. changed from 4-10-23. |
| 4/4/2023 3:00:00 PM |
COMMENTS/RESPONSES DUE |
Company response to bench reqeust due by 3pm. |
| 4/3/2023 |
STAFF WORKSHOP |
GRR Staff and Intervenor Workshop Questions to Company specifics TBD. |
| 3/17/2023 |
EFFECTIVE DATE/ STATUTORY DEADLINE |
|
| 3/8/2023 10:00:00 AM |
CONFERENCE |
Notice of Prehearing Conference. Copies servered on 2/24/23. |
| | Location: ZOOM |