Docket No:  UE 416 Docket Name:  PGE REQUEST FOR A GENERAL RATE REVISION Submit Public Comment
* This docket is a contested case. See the Internal Operating Guidelines and OAR 860-001
Subject Company:  PORTLAND GENERAL ELECTRIC    
In the Matter of PORTLAND GENERAL ELECTRIC COMPANY, Request for a General Rate Revision; and 2024 Annual Power Cost Update. Filed by Shay LaBray. Copies served to Electric Industry List.
Filing Date:  2/8/2023 Advice No: 23-40      
Effective:  1/1/2024 Expiration:  12/17/2023 Status:  ACCEPTED
Order:  23-482Order Signed:  12/21/2023 
Email Service List (semi-colon delimited)      Email Service List (comma delimited)
  If you experience problems with the above 'Email Service List' links,
please try one of these:
Service List Popup (semi-colon delimited)     Service List Popup (comma delimited)
General information about Tariff Filings.

ACTIONSSERVICE LISTSCHEDULE Public Comments
Date/TimeEventDescription
1/1/2024 EFFECTIVE DATE/ STATUTORY DEADLINE GRR Effective date 1/1/2024.
1/1/2024 EFFECTIVE DATE/ STATUTORY DEADLINE
1/1/2024 EFFECTIVE DATE/ STATUTORY DEADLINE
1/1/2024 EFFECTIVE DATE/ STATUTORY DEADLINE
1/1/2024 EFFECTIVE DATE/ STATUTORY DEADLINE
1/1/2024 EFFECTIVE DATE/ STATUTORY DEADLINE
12/18/2023 FINAL ORDER DUE DATE 5th Partial Stip-Target Order Date
12/18/2023 FINAL ORDER DUE DATE GRR Commission Order (target)
12/17/2023 EXPIRATION DATE
12/6/2023 3:00:00 PM COMMENTS/RESPONSES DUE Parites repsonse to 7th bench request due by 3pm.
11/30/2023 3:00:00 PM COMMENTS/RESPONSES DUE PGE response 7th Bench Request due by 3pm
11/17/2023 3:00:00 PM COMMENTS/RESPONSES DUE 5th Partial Stip-AWEC’s Reply to 5th partial Stip due by 3pm.
11/15/2023 3:00:00 PM COMMENTS/RESPONSES DUE PGE's responses to bench request 5-8 are due with November 15 MONET updates.
11/9/2023 3:00:00 PM COMMENTS/RESPONSES DUE Fifth partial stipulation-Stipulating parties response due by 3pm.
11/8/2023 3:00:00 PM COMMENTS/RESPONSES DUE Fifth partial stipulation Deadline to request further process due by 3pm
11/7/2023 3:00:00 PM COMMENTS/RESPONSES DUE PGE's responses to bench request 5-8 are due with the company's November 7 MONET update.
10/24/2023 3:00:00 PM COMMENTS/RESPONSES DUE Parties responses to Bench Request 5-1 through 5-7, and 5-9 due by 3pm.
10/23/2023 3:00:00 PM COMMENTS/RESPONSES DUE Parties response to Bench Reqeust #4 due by 3pm.
10/20/2023 3:00:00 PM COMMENTS/RESPONSES DUE PGE responses to bench requests 5-1 through 5-7, and 5-9 due by 3pm.
10/20/2023 3:00:00 PM COMMENTS/RESPONSES DUE Parties repsonse to 3rd bench request due by 3pm.
10/18/2023 3:00:00 PM COMMENTS/RESPONSES DUE PGE's response due for Bench Reqeust #4 due by 3pm.
10/16/2023 3:00:00 PM COMMENTS/RESPONSES DUE Parties response to SBUA case certification request and proposed budget due
10/16/2023 3:00:00 PM COMMENTS/RESPONSES DUE Company repsonse to 3rd bench request due by 3pm.
10/11/2023 3:00:00 PM STIPULATION DUE Stipulation due or status updated due by 3pm.
9/15/2023 3:00:00 PM ISSUE STATEMENT DUE GRR Issues Lists and Position Statements (all parties) due by 3pm.
9/11/2023 3:00:00 PM TESTIMONY/EXHIBITS DUE GRR Company Surrebuttal Testimony due by 3pm.
9/11/2023 3:00:00 PM BRIEF DUE APCU Staff and Intervenor Reply Briefs due by 3pm.
9/8/2023 3:00:00 PM TESTIMONY/EXHIBITS DUE AWEC's Supplemental Rebuttal Testimony due by 3pm.
8/28/2023 3:00:00 PM BRIEF DUE APCU Company Opening Brief due by 3pm
8/23/2023 3:00:00 PM STIPULATION DUE Partial stipulations and supporting testimony due by 3pm.
8/23/2023 3:00:00 PM TESTIMONY/EXHIBITS DUE Outstanding partial stipulations and supporting testimony due by 3pm.
8/22/2023 3:00:00 PM TESTIMONY/EXHIBITS DUE GRR Staff and Intervenor Rebuttal Testimony due by 3pm.
8/14/2023 3:00:00 PM CROSS EXAMINATION STATEMENT DUE Cross-Examination Statements due by 3:00 pm
8/14/2023 3:00:00 PM TESTIMONY/EXHIBITS DUE Cross-Examination Testimony and Exhibits due by 3pm
8/14/2023 3:00:00 PM CROSS EXAMINATION STATEMENT DUE APCU Cross-Examination Statements due by 3pm.
8/10/2023 3:00:00 PM TESTIMONY/EXHIBITS DUE APCU Company Surrebuttal Testimony due by 3pm.
8/1/2023 SETTLEMENT CONFERENCE GRR Settlement Conference specifics TBD.
7/21/2023 3:00:00 PM TESTIMONY/EXHIBITS DUE GRR Company Reply Testimony due by 3pm.
7/21/2023 3:00:00 PM TESTIMONY/EXHIBITS DUE APCU Staff and Intervenor Rebuttal Testimony due by 3pm
6/28/2023 SETTLEMENT CONFERENCE GRR Staff led Settlement Conference specifics TBD.
6/21/2023 3:00:00 PM TESTIMONY/EXHIBITS DUE APCU Company Reply Testimony due by 3pm.
6/14/2023 SETTLEMENT CONFERENCE APCU Settlement Conference specifics TBD.
6/13/2023 3:00:00 PM TESTIMONY/EXHIBITS DUE GRR Staff and Intervenor Opening Testimony due by 3pm.
6/6/2023 3:00:00 PM COMMENTS/RESPONSES DUE Parties may submit replies to PGE's responses
5/30/2023 3:00:00 PM COMMENTS/RESPONSES DUE PGE to Submit Filing Responding to 5/23/23 ALJ Memorandum
5/24/2023 3:00:00 PM TESTIMONY/EXHIBITS DUE APCU Staff and Intervenor Opening Testimony due by 3pm.
5/3/2023 6:00:00 PM PUBLIC COMMENT HEARING Notice of Public Comment Hearing. Copies served to service list on 4/14/23.
 Location:  ZOOM WEBINAR
4/28/2023 MISCELLANEOUS Intervenor Funding - Justice Case Funding - Target date for Commission Decisions regarding case certification
4/21/2023 SETTLEMENT CONFERENCE GRR Settlement Conference specifics TBD.
4/18/2023 3:00:00 PM COMMENTS/RESPONSES DUE Parties response to bench request due by 3 pm.
4/14/2023 STAFF WORKSHOP APCU Staff Workshop specifics TBD.
4/13/2023 3:00:00 PM STAFF WORKSHOP GRR Staff Workshop specifics TDB. changed from 4-10-23.
4/4/2023 3:00:00 PM COMMENTS/RESPONSES DUE Company response to bench reqeust due by 3pm.
4/3/2023 STAFF WORKSHOP GRR Staff and Intervenor Workshop Questions to Company specifics TBD.
3/17/2023 EFFECTIVE DATE/ STATUTORY DEADLINE
3/8/2023 10:00:00 AM CONFERENCE Notice of Prehearing Conference. Copies servered on 2/24/23.
 Location:  ZOOM

 