Docket No:
UE 427
Docket Name:
PGE RENEWABLE RESOURCE AUTOMATIC ADJUSTMENT CLAUSE (SCHEDULE 122) (CLEARWATER)
Submit Public Comment
* This docket is a contested case. See the
Internal Operating Guidelines
and
OAR 860-001
Subject Company:
PORTLAND GENERAL ELECTRIC
In the Matter of PORTLAND GENERAL ELECTRIC COMPANY, Renewable Resource Automatic Adjustment Clause (Schedule 122) (Clearwater Wind Project). Filed by Robert Macfarlane. Copies served to ELECTRIC Notification List.
Filing Date:
10/30/2023
Advice No:
23-20
Effective:
10/1/2024
Expiration:
9/30/2024
Status:
SUSPENDED
Case Manager:
RAWLEIGH WHITE
Phone:
971-301-0089
Email:
rawleigh.white@puc.oregon.gov
Law Judge:
ALISON LACKEY
Phone:
503-400-2861
Email Service List (semi-colon delimited)
Email Service List (comma delimited)
If you experience problems with the
above
'Email Service List' links,
please try one of these:
Service List Popup (semi-colon delimited)
Service List Popup (comma delimited)
ACTIONS
SERVICE LIST
SCHEDULE
Public Comments
Date/Time
Event
Description
10/1/2024
EFFECTIVE DATE/ STATUTORY DEADLINE
See Order No. 24-134.
9/30/2024
EXPIRATION DATE
9/23/2024
FINAL ORDER DUE DATE
Target Date for Commission Decision
8/23/2024 3:00:00 AM
BRIEF DUE
PGE Reply Brief
8/9/2024 3:00:00 PM
BRIEF DUE
Staff/intervenor reply briefs
7/26/2024 3:00:00 PM
BRIEF DUE
All Parties Opening Briefs
7/11/2024 9:30:00 AM
HEARING
Details to be provided
7/2/2024 3:00:00 PM
CROSS EXAMINATION STATEMENT DUE
All Parties Cross-examination Statements
6/24/2024 3:00:00 PM
TESTIMONY/EXHIBITS DUE
PGE surrebuttal
5/29/2024 3:00:00 PM
TESTIMONY/EXHIBITS DUE
Intervenor testimony
4/30/2024 3:00:00 PM
MISCELLANEOUS
Procedural schedules are due no later than 3:00 p.m.
4/25/2024 3:00:00 PM
TESTIMONY/EXHIBITS DUE
PGE Reply Testimony
3/26/2024 3:00:00 PM
STIPULATION DUE
Stipulation, Supporting Testimony, with Motions to Admit due
3/26/2024 3:00:00 PM
MISCELLANEOUS
Status Report due if Stipulation is not filed.
3/14/2024 3:00:00 PM
COMMENTS/RESPONSES DUE
Parties reponse to Bench Request due by 3pm.
3/12/2024 3:00:00 PM
COMMENTS/RESPONSES DUE
Company response to Bench Request due by 3pm.
2/6/2024 3:00:00 PM
TESTIMONY/EXHIBITS DUE
Staff and Intervenor Opening Testimony due by 3pm.
11/13/2023 3:00:00 PM
COMMENTS/RESPONSES DUE
Parties may file a Response or an Intent to Respond to PGE's Motion for Modified Protective Order