eDockets
Docket Summary
Return to Search Page eFiling

Docket No:  ADV 1662 Docket Name:  PGE ADVICE NO. 24-28 SCHEDULE 146 COLSTRIP POWER PLANT OPERATING LIFE ADJUSTMENT Submit Public Comment
Subject Company:  PORTLAND GENERAL ELECTRIC    
PGE Advice No. 24-28, Schedule 146 Colstrip Power Plant Operating Life Adjustment. The purpose of this filing is to adjust Customer rates for recovery of the 2025 revenue requirement for PGE's ownership share of the Colstrip generation plant.
Filing Date:  11/1/2024 Advice No: 24-28      
Effective:  1/1/2025 Expiration:   Status:  PENDING
Case Manager:  MING PENG Phone:  503-508-3040
Email:   ming.peng@puc.oregon.gov
Email Service List (semi-colon delimited)      Email Service List (comma delimited)
  If you experience problems with the above 'Email Service List' links,
please try one of these:
Service List Popup (semi-colon delimited)     Service List Popup (comma delimited)

ACTIONSSERVICE LISTSCHEDULE Public Comments
Sort By Date        Sort By Type
Date: 11/6/2024 Action:  REPLACEMENT SHEETS, ADDITIONAL MATERIAL  Searchable Doc  
  Description
PGE Supplemental Filing of Advice No. 24-28, Schedule 146 Colstrip Power Plant Operating Life Adjustment. PGE is submitting this Supplemental Filing because it discovered that the Generation Base Revenues (which are used to allocate the Schedule 146 Revenue Requirement) for Schedules 89-P were calculated using the Schedule 85-P Net Variable Power Cost (NVPC) prices instead of the Schedule 89-P NVPC prices. This filing corrects the calculations, so that all Generation Base Revenues for these Schedules are correctly calculated. 
Date: 11/1/2024 Action:  INITIAL UTILITY FILING  Searchable Doc  
  Description
PGE Advice No. 24-28, Schedule 146 Colstrip Power Plant Operating Life Adjustment. The purpose of this filing is to adjust Customer rates for recovery of the 2025 revenue requirement for PGE's ownership share of the Colstrip generation plant.