Docket No:  UE 158 Docket Name:  INVESTIGATION INTO TARIFFS FOR SUPPLEMENTAL AND BACKUP POWER Submit Public Comment
Subject Company:  PORTLAND GENERAL ELECTRIC    
         See also:  03-19   04-15
In the Matter of PORTLAND GENERAL ELECTRIC COMPANY Stand-by Service for Supplemental and Backup Power for Large Customers with On-Site Generation. Filed by Pamela G. Lesh.
Filing Date:  10/22/2003      
Order:  04-400Order Signed:  7/19/2004 
Email Service List (semi-colon delimited)      Email Service List (comma delimited)
  If you experience problems with the above 'Email Service List' links,
please try one of these:
Service List Popup (semi-colon delimited)     Service List Popup (comma delimited)

ACTIONSSERVICE LISTSCHEDULE Public Comments
Sort By Date        Sort By Type
Date: 7/19/2004 Action:  ORDER  Getdocs  
  Order No:   04-400 
  Description
Order No. 04-400 signed by Commissioners Lee Beyer, John Savage, and Ray Baum; Disposition: STIPULATION ADOPTED. Copies served 7/22/04. 
Date: 6/28/2004 Action:  TESTIMONY & EXHIBITS   
  Description
PORTLAND GENERAL ELECTRIC and STAFF's Joint Party Testimony in Support of Stipulation and Settlement. FAXED by J. Richard George. 
Date: 6/28/2004 Action:  STIPULATION   
  Description
PORTLAND GENERAL ELECTRIC , STAFF, SP NEWSPRINT, OREGON DEPARTMENT OF ENERGY and the INDUSTRIAL CUSTOMERS OF NORTHWEST UTILITIES' Joint Stipulation and Settlement (with supporting Exhibits). FAXED by J. Richard George. Hard copy rec'd 6/30/04. 
Date: 5/21/2004 Action:  CANCELLATION/CHANGE  Searchable Doc  
  Description
ALJ Thomas Barkin issues Notice of Cancellation of Prehearing Conference scheduled for May 24, 2004. Copies served electronically and via mail on 5/21/04. 
Date: 5/18/2004 Action:  MOTION   
  Description
STAFF's motion to suspend further events in the schedule to allow for further settlement discussions; Filed by Michael T. Weirich. 
Date: 5/17/2004 Action:  ISSUE STATEMENT   
  Description
INDUSTRIAL CUSTOMERS OF NORTHWEST UTILITIES' Issues List; FAXED by Christian W. Griffen. Hard copy rec'd 5/18/04. 
Date: 5/12/2004 Action:  CONFERENCE  Searchable Doc  
  Description
PREHEARING CONFERENCE scheduled 5/24/2004 9:30 AM City: SALEM Room: MAIN HEARING RM--1ST FLR Building: PUC Address: 550 CAPITOL ST NE Reporter: NONE Law Judge: BARKIN, TOM Notice of Prehearing Conference served electronically on 5/12/04 and via mail on 5/13/04.  
Date: 5/11/2004 Action:  LAW JUDGE RULING/MEMORANDA  Searchable Doc  
  Description
ALJ Thomas Barkin issues ruling granting parties' request for modification to the schedule in this docket. Copies served electronically and via mail on 5/11/04. 
Date: 4/28/2004 Action:  OTHER FILING/PLEADING   
  Description
STAFF's letter correcting the date of the prehearing conference from May 26, 2004 to May 24, 2004. Filed by Michael T. Weirich. 
Date: 4/28/2004 Action:  LAW JUDGE RULING/MEMORANDA   
  Description
ALJ Thomas Barkin issues ruling (electronically) granting joint Parties' motion to modify the schedule, including a fifth settlement workshop (May 10, 2004). A written ruling will follow. Served electronically only.  
Date: 4/27/2004 Action:  MOTION   
  Description
STAFF and active Parties' letter (joint motion) requesting modification to the schedule, including a fifth settlement workshop (May 10, 2004). Filed by Michael T. Weirich. 
Date: 3/25/2004 Action:  CONFERENCE   
  Description
CONFERENCE scheduled 5/24/2004 City: SALEM Room: MAIN HEARING RM--1ST FLR Building: PUC Address: 550 CAPITOL ST NE Reporter: NONE Law Judge: BARKIN, TOM Prehearing conference.  
Date: 3/24/2004 Action:  LAW JUDGE RULING/MEMORANDA  Searchable Doc  
  Description
ALJ Thomas Barkin issues ruling modifying the schedule as follows: Settlement workshop = April 26, 2004; Parties submit list of disputed issues = May 10, 2004; Prehearing conference = May 24, 2004. Copies served electronically and via mail on 3/24/04.  
Date: 3/19/2004 Action:  OTHER FILING/PLEADING   
  Description
STAFF's letter requesting an ALJ ruling with schedule modification; filed by Michael T. Weirich. 
Date: 2/25/2004 Action:  SIGNATORY PAGES   
  Description
PORTLAND GENERAL ELECTRIC 's Signatory Page to Protective Order No. 04-032 executed by Hethie Parmesano; filed by J. Jeffrey Dudley. 
Date: 2/25/2004 Action:  LAW JUDGE RULING/MEMORANDA   
  Description
ALJ Thomas Barkin issues Ruling adopting the following modified schedule: Settlement workshop = March 18, 2004; Parties submit list of disputed issues = March 31, 2004; Prehearing conference = April 7, 2004. Copies served electronically and via mail on 2/25/04.  
Date: 2/19/2004 Action:  MOTION   
  Description
STAFF's letter requesting a Stipulated Change of Schedule; filed by Michael T. Weirich. 
Date: 2/12/2004 Action:  SIGNATORY PAGES   
  Description
INDUSTRIAL CUSTOMERS OF NORTHWEST UTILITIES' Signatory page to Protective Order No. 04-032 executed by S. Bradley Van Cleve, Melinda J. Davison, Irion A. Sanger, Matthew W. Perkins, Ruth A. Miller, Christian W. Griffen, Erin K. McDonough and Lincoln Wolverton; FAXED by Christian W. Griffen on behalf of S. Bradley Van Cleve. Hard copy rec'd 2/13/04. 
Date: 2/10/2004 Action:  CONFERENCE   
  Description
PREHEARING CONFERENCE scheduled 3/3/2004 9:35 AM City: SALEM Room: SMALL HEARING RM Building: PUC Address: 550 CAPITOL ST NE Reporter: NONE Law Judge: BARKIN, TOM Dial-In # 503-378-3313. Notice of Prehearing Conference served electronically and via mail on 2/10/04.  
Date: 2/9/2004 Action:  SIGNATORY PAGES   
  Description
SP NEWSPRINT CO.'s Signatory pages from Protective Order No. 04-032 executed by Mark Rawlings, Thomas M. Grim, J. Laurence Cable, Tamara L. Faucette, Rhonda L. Roth, Mark Rawlings, Michelle Thornhill, and Bruce Craig. Filed by Thomas M. Grim. 
Date: 2/2/2004 Action:  SIGNATORY PAGES   
  Description
PORTLAND GENERAL ELECTRIC 's Signatory pages from Protective Order No. 04-032 executed by J. Jeffrey Dudley, J. Richard George, Bari H. Gilbert, Adam Menendez, Marc A. Cody, Mary Tavares, Judy Froedge, Jack Donaldson, Sara Cardwell, Randy Dahlgren, Ted Drennan, Doug Kuns, Craig Zuck and Joe Taylor; filed by J. Jeffrey Dudley. 
Date: 1/27/2004 Action:  LAW JUDGE RULING/MEMORANDA   
  Description
ALJ Thomas Barkin issues ruling granting petitions to intervene of PacifiCorp, SP Newsprint, and the Oregon Department of Energy. Copies served electronically and via mail on 1/27/04. 
Date: 1/21/2004 Action:  PETITION TO INTERVENE   
  Description
OREGON DEPARTMENT OF ENERGY's Petition to Intervene; FAXED by Janet L. Prewitt. Hard copy rec'd 1/22/04. 
Date: 1/21/2004 Action:  MOTION   
  Description
OREGON DEPARTMENT OF ENERGY's Motion to Intervene Out of Time; FAXED by Janet L. Prewitt. Hard copy rec'd 1/22/04. 
Date: 1/20/2004 Action:  PETITION TO INTERVENE   
  Description
SP NEWSPRINT COMPANY's Petition to Intervene; FAXED by Thomas M. Grim. Hard copy rec'd 1/22/04. 
Date: 1/20/2004 Action:  PROTECTIVE ORDER  Getdocs  
  Order No:   04-032 
  Description
Protective Order No. 04-032 signed by Thomas G. Barkin, served to service list on 1/21/04. 
Date: 1/13/2004 Action:  PETITION TO INTERVENE   
  Description
PACIFICORP's Petition to Intervene; FAXED by Katherine A. McDowell. Hard copy rec'd 1/14/04. 
Date: 1/12/2004 Action:  NOTICE   
  Description
STAFF's Notice of Workshops; filed by Lisa Schwartz. 
Date: 1/6/2004 Action:  LAW JUDGE RULING/MEMORANDA   
  Description
ALJ Thomas Barkin issues memorandum setting the following schedule: Deadline for petitions to intervene = January 20, 2004; Settlement workshop I = January 26, 2004 (morning); Settlement workshop II = February 18, 2004 (morning); Parties file list of disputed issues = February 25, 2004; Prehearing conference = March 3, 2004 Copies served electronically on 1/6/04, and via mail on 1/7/04 to service list; and copies served via mail to AHD Electric service list on 1/14/04.  
Date: 12/29/2003 Action:  PETITION TO INTERVENE   
  Description
INDUSTRIAL CUSTOMERS OF NORTHWEST UTILITIES' Petition to Intervene; FAXED by Christian Griffen on behalf of S. Bradley Van Cleve. Hard copy rec'd 12/30/03. 
Date: 12/22/2003 Action:  CONFERENCE   
  Description
PREHEARING CONFERENCE scheduled 1/5/2004 9:30 AM City: SALEM Room: SMALL HEARING RM Building: PUC Address: 550 CAPITOL ST NE Reporter: NONE Law Judge: BARKIN, TOM Notice of Prehearing Conference served electronically 12/22/03 and via mail on 12/23/03 to UE 158 and AHD ELECTRIC service lists.  
Date: 12/5/2003 Action:  OTHER FILING/PLEADING   
  Description
Staff report for December 4, 2003 Public Meeting (Item No. 4); Filed by Lisa Schwartz. 
Date: 10/22/2003 Action:  INITIAL (APPLICATION, COMPLAINT, PETITION)   
  Description
In the Matter of PORTLAND GENERAL ELECTRIC COMPANY Stand-by Service for Supplemental and Backup Power for Large Customers with On-Site Generation. Filed by Pamela G. Lesh.