Sort By Date
Sort By Type
|
Date: |
11/30/2021 |
Action: ORDER |
|
|
Order No:
21-443 |
|
Description
ARB 497(6) - Order No. 21-443 signed by Nolan Moser, Chief Administrative Law Judge, Administrative Hearings Division; DISPOSITION: STAFF'S RECOMMENDATION ADOPTED. Copies served on 12/01/21. |
Date: |
11/24/2021 |
Action: STAFF REPORT |
|
|
Description
ARB 497(6) - Staff Report for the November 30, 2021 Public Meeting (Item No. CA17) filed by Bret Farrell. |
Date: |
10/1/2021 |
Action: SUPPLEMENTAL APPLICATION |
|
|
Description
ARB 497(6) - In the Matter of HUNTER CONSTRUCTION, INC., dba HUNTER COMMUNICATIONS and dba CORE DIGITAL SERVICES and QWEST CORPORATION d/b/a CENTURYLINK QC. Sixth Amendment to Interconnection Agreement (FCC Modernizing Unbundling and Resale Requirements), Submitted for Commission Approval Pursuant to Section 252(e) of the Telecommunications Act of 1996. Filed by Josie Addington. |
Date: |
9/10/2013 |
Action: OTHER CORRESPONDENCE (ACKN, SVC, LTR) |
|
|
Description
ARB 907 REPLACES ARB 497. |
Date: |
9/2/2008 |
Action: ORDER |
|
|
Order No:
08-440 |
|
Description
ARB 497(5) - Order No. 08-440 signed by Michael Grant, Chief Administrative Law Judge, Administrative Hearings Division; Disposition: Amendment and Agreements Approved.
Copies electronically served 9/4/08. |
Date: |
8/19/2008 |
Action: OTHER FILING/PLEADING |
|
|
Description
ARB 497(5) - Staff Report for 8/26/08 Public Meeting (Item No. CA4); filed by Celeste Hari.
(Electronic version available at: www.puc.state.or.us/Public Meetings/Public Meeting Agenda). |
Date: |
7/28/2008 |
Action: LAW JUDGE RULING/MEMORANDA |
|
|
Description
ARB 497(5)-ARB 842 -- Chief ALJ Michael Grant's ruling regarding 7/11/08 letter to Hunter Communications, Inc. - No response from Hunter Communications - proceed on routine basis.
Copies served electronically and via mail 7/28/08. |
Date: |
5/23/2008 |
Action: AMENDED (APPLICATION, COMPLAINT, PETITION) |
|
|
Description
ARB 497(5) -
In the Matter of
HUNTER CONSTRUCTION, INC. and QWEST CORPORATION
Fifth Amendment (TRO-TRRO2) to Interconnection Agreement, Submitted for Commission Approval Pursuant to Section 252(e) of the Telecommunications Act of 1996. Electronically filed by Carla Butler.
Hard copy rec'd. 5/27/08.
(See 7/28/08 ALJ Ruling for further information.) |
Date: |
9/27/2006 |
Action: ORDER |
|
|
Order No:
06-557 |
|
Description
ARB 497(4) - Order No. 06-557 signed by Michael Grant, Chief Administrative Law Judge, Administrative Hearings Division; Disposition: Amendment Approved.
Copies electronically served 9/29/06. |
Date: |
8/18/2006 |
Action: COMMENTS/RESPONSE |
|
|
Description
ARB 497(4) - Staff's Comments; filed by Celeste Hari. |
Date: |
8/2/2006 |
Action: SUPPLEMENTAL APPLICATION |
|
|
Description
ARB 497(4) -
In the Matter of
HUNTER COMMUNICATIONS INC. dba HUNTER COMMUNICATIONS dba CORE DIGITAL SERVICES and QWEST CORPORATION
Fourth Amendment (Rate Update-Fiber) to Interconnection Agreement, Submitted for Commission Approval Pursuant to Section 252(e) of the Telecommunications Act of 1996. Electronically filed by Carla Butler.
Hard copy rec'd. 8/3/06.
Comments Due 8/23/06. |
Date: |
1/13/2005 |
Action: ORDER |
|
|
Order No:
05-036 |
|
Description
ARB 497(3) - Order No. 05-036 signed by Michael Grant, Administrative Law Judge, Administrative Hearings Division; Disposition: Amendment Approved.
Copies electronically served 1/20/05. |
Date: |
1/10/2005 |
Action: SUPPLEMENTAL APPLICATION |
|
|
Description
ARB 497(3) -
In the Matter of
HUNTER CONSTRUCTION INC and QWEST CORPORATION
Third Amendment (special promo) to Interconnection Agreement, Submitted for Commission Approval Pursuant to Section 252(e) of the Telecommunications Act of 1996. Filed by Carla Butler.
Order due = 1/20/05.
|
Date: |
9/2/2004 |
Action: ORDER |
|
|
Order No:
04-499 |
|
Description
ARB 497 (1 & 2) - Order No. 04-499 signed by Lee Sparling, Director of Utility Program; DISPOSITION: AGREEMENT APPROVED.
Copies served electronically on 9/4/04. |
Date: |
7/6/2004 |
Action: COMMENTS/RESPONSE |
|
|
Description
ARB 497(2)-Staff's Comments; filed by Celeste Hari. |
Date: |
7/1/2004 |
Action: COMMENTS/RESPONSE |
|
|
Description
ARB 497(1) - Staff's Comments; filed by Celeste Hari. |
Date: |
6/14/2004 |
Action: SUPPLEMENTAL APPLICATION |
|
|
Description
ARB 4978(2) -
In the Matter of
HUNTER CONSTRUCTION INC and QWEST CORPORATION
Second Amendment (Special Promo Collocation) to Interconnection Agreement, Submitted for Commission Approval Pursuant to Section 252(e) of the Telecommunications Act of 1996. Filed by Carla Butler.
Comments Due = 7/6/04.
|
Date: |
6/14/2004 |
Action: SUPPLEMENTAL APPLICATION |
|
|
Description
ARB 497(1) -
In the Matter of
HUNTER CONSTRUCTION INC and QWEST CORPORATION
First Amendment (Collocation Available Inventory) to Interconnection Agreement, Submitted for Commission Approval Pursuant to Section 252(e) of the Telecommunications Act of 1996. Filed by Carla Butler.
Comments Due = 7/6/04.
|
Date: |
9/29/2003 |
Action: ORDER |
|
|
Order No:
03-582 |
|
Description
ARB 497 -- Order No. 03-582, signed by Lee Sparling, Acting Director, Utility Program; DISPOSITION: AGREEMENT APPROVED.
Copies served electronically 10/2/03. |
Date: |
7/29/2003 |
Action: COMMENTS/RESPONSE |
|
|
Description
ARB 497 -- Staff Comments; Filed by Celeste Hari. |
Date: |
7/16/2003 |
Action: INITIAL (APPLICATION, COMPLAINT, PETITION) |
|
|
Description
In the Matter of
HUNTER CONSTRUCTION, INC., dba HUNTER COMMUNICATIONS and dba CORE DIGITAL SERVICES and QWEST CORPORATION
Negotiated Interconnection Agreement (SGAT-9th Rev.), Submitted Pursuant to Section 252(e) of the Telecommunications Act of 1996. Filed by Jamaica Wilson.
Comments Due = August 6, 2003.
|