Sort By Date
Sort By Type
|
Date: |
10/6/2000 |
Action: ORDER |
|
|
Order No:
00-620 |
|
Description
Order No. 00-620 signed by Chairman Ron Eachus, Commissioner Roger Hamilton, and Commissioner Joan H. Smith. DISPOSITION: REVISED CURTAILMENT PLAN APPROVED WITH CONDITIONS
IT IS ORDERED that the filing of Portland General Electric Company for approval of its revised Rule M Curtailment Plan is granted, subject to the conditions set forth on page 3 of Appendix A (Staff Report for public meeting 9/12/00).
Copies served to general electric service list 10/10/00. |
Date: |
9/12/2000 |
Action: OTHER FILING/PLEADING |
|
|
Description
Staff report for 9/12/00 public meeting (Regular Agenda No. 5) recommending the Commission approve PGE's filing to add the short-term system emergency curtailment plan to Rule M subject to the following conditions: 1. After calling a system emergency PGE shall submit a brief report to the Commission describing the conditions that lead it to believe that an emergency was imminent, and the actions taken during the emergency. 2. Should the Commission find that calling the emergency was not warranted, the Commission shall take action it deems appropriate. 3. PGE shall only call a system emergency when there is a condition that violates Willamette Valley/Southwest Washington Area (WILSWA) procedures or WSCC rules or standards, or that threatens damage to PGE equipment or that threatens the widespread loss of PGE loads. 4. PGE has authority to call a system emergency without prior notice to the PUC only for situations in which prior notice is impracticable. 5. PGE cannot initiate a system emergency to avoid purchasing high priced power.
Filed by Stefan Brown. |
Date: |
9/12/2000 |
Action: OTHER FILING/PLEADING |
|
|
Description
PORTLAND GENERAL ELECTRIC COMPANY's Supporting Materials to Initial Application. PGE Load Shedding Procedures Overview (dated 7/26/00) and Attachments A-E: A/WILSWA Voltage Stability Operating Procedure; B/Underfrequency Load Shed-Restore Procedures; C/Critical Feeders Criteria List - Priority Rankings; D/Rolling Curtailment List; E/Critical Feeders. Filed by R. J. Dahlgren. [Received in AHD 9/12/00]. |
Date: |
9/12/2000 |
Action: INITIAL (APPLICATION, COMPLAINT, PETITION) |
|
|
Description
In the Matter of PORTLAND GENERAL ELECTRIC COMPANY's Revised Tariff Sheets to Add a Short-Term System Emergency Curtailment Plan to Rule M. Filed by Pamela G. Lesh (dated 5/15/00). [Received in AHD 9/12/00]. |
Date: |
9/12/2000 |
Action: ALLOWED (APPROVED) UTILITY FILING |
|
|
Description
Filing allowed. |
Date: |
8/11/2000 |
Action: REPLACEMENT SHEETS, EXTENSION |
|
|
Description
The company requested an extension of the effective date to 9/13/00. |
Date: |
7/26/2000 |
Action: REPLACEMENT SHEETS, ADDITIONAL MATERIAL |
|
|
Description
The company requested extension of the effective date to 8/25/00, and filed a revised copy of the Overview describing PGE's Load Shedding Procedures.. |
Date: |
6/14/2000 |
Action: REPLACEMENT SHEETS, EXTENSION |
|
|
Description
The company requested extension of effective date to 8/9/00. |
Date: |
5/15/2000 |
Action: INITIAL UTILITY FILING |
|
|
Description
This filing adds the short-term system emergency curtailment plan to Rule M. |