Sort By Date
Sort By Type
|
Date: |
12/28/2023 |
Action: SUPPLEMENTAL APPLICATION |
|
|
Description
UM 2218(2) - In the Matter of PORTLAND GENERAL ELECTRIC COMPANY, Application for Reauthorization to Defer Costs and Revenues Associated with the Transportation Electrification Charge. Filed by Jaki Ferchland.
Sent to the Electric List. |
Date: |
8/9/2023 |
Action: ORDER |
|
|
Order No:
23-287 |
|
Description
Order No. 23-287, signed by Nolan Moser, Chief Administrative Law Judge; DISPOSITION: STAFF'S RECOMMENDATION ADOPTED. Copies served on 8/9/23. |
Date: |
8/3/2023 |
Action: STAFF REPORT |
|
|
Description
UM 2218(1) - Staff Report for the August 8, 2023 Public Meeting (Item No. CA3), by Kathy Zarate. |
Date: |
12/30/2022 |
Action: SUPPLEMENTAL APPLICATION |
|
|
Description
UM 2218(1) - In the Matter of PORTLAND GENERAL ELECTRIC COMPANY, Application for Reauthorization to Defer Costs and Revenues Associated with the Transportation Electrification Charge. Filed by Jaki Ferchland.
Sent to the Electric List. |
Date: |
10/19/2022 |
Action: SERVICE LIST CHANGE |
|
|
Description
PGE's Request to Change to Service Lists, removing Loretta I. Mabinton and Adding Kim S. Burton; filed by Kim S. Burton. |
Date: |
6/2/2022 |
Action: ORDER |
|
|
Order No:
22-200 |
|
Description
Order No. 22-200 signed by Chief Administrative Law Judge Nolan Moser; DISPOSITION: STAFF'S RECOMMENDATION ADOPTED.
Copies served 6/3/22 |
Date: |
5/26/2022 |
Action: STAFF REPORT |
|
|
Description
Staff Report for the May 31, 2022 Public Meeting (Item No. CA8); filed by Curtis Dlouhy. |
Date: |
12/30/2021 |
Action: INITIAL (APPLICATION, COMPLAINT, PETITION) |
|
|
Description
In the Matter of PORTLAND GENERAL ELECTRIC COMPANY, Application for Deferral of Costs and Revenues Associated with the Transportation Electrification Charge. Filed by Jaki Ferchland.
Sent to the Electric List. |