Docket No:
ADV 653
Docket Name:
PGE ADVICE NO. 17-29, SCHEDULE 135 DEMAND RESPONSE COST RECOVERY MECHANISM
Submit Public Comment
Subject Company:
PORTLAND GENERAL ELECTRIC
PGE's Advice No. 17-29, Schedule 135 Demand Response Cost Recovery Mechanism. The purpose of this filing is to update the Schedule 135 prices consistent with the existing balance for Automated Demand Response; projections of costs for Schedules 4, 25,...
Filing Date:
11/13/2017
Advice No:
17-29
Public Mtg:
12/18/2017
Effective:
1/1/2018
Expiration:
Status:
ACKNOWLEDGED
Case Manager:
Mitch Moore
Phone:
971-375-5094
Email:
mitch.moore@puc.oregon.gov
Staff Contact:
JASON KLOTZ
Phone:
503-378-6667
Email:
jason.klotz@state.or.us
If you experience problems with the
above
'Email Service List' links,
please try one of these:
Service List Popup (semi-colon delimited)
Service List Popup (comma delimited)
General information about Tariff Filings.
ACTIONS
SERVICE LIST
SCHEDULE
Public Comments
Sort By Date
Sort By Type
Date:
12/22/2017
Action:
ACKNOWLEDGED UTILITY FILING
Description
Letter emailed.
Date:
12/18/2017
Action:
STAFF REPORT
Description
Staff report written by Mitchell Moore for 12/18/17 public meeting.
Date:
11/13/2017
Action:
INITIAL UTILITY FILING
Description
PGE's Advice No. 17-29, Schedule 135 Demand Response Cost Recovery Mechanism. The purpose of this filing is to update the Schedule 135 prices consistent with the existing balance for Automated Demand Response; projections of costs for Schedules 4, 25, and 26; and projected 2018 applicable loads.