eDockets
Docket Summary
***If sending a message to PUC staff, please note that as of March 29, 2021, all emails end with @puc.oregon.gov (instead of @state.or.us).
Docket No:
ADV 653
Docket Name:
PGE ADVICE NO. 17-29, SCHEDULE 135 DEMAND RESPONSE COST RECOVERY MECHANISM
Submit Public Comment
Subject Company:
PORTLAND GENERAL ELECTRIC
PGE's Advice No. 17-29, Schedule 135 Demand Response Cost Recovery Mechanism. The purpose of this filing is to update the Schedule 135 prices consistent with the existing balance for Automated Demand Response; projections of costs for Schedules 4, 25,...
Filing Date:
11/13/2017
Advice No:
17-29
Public Mtg:
12/18/2017
Effective:
1/1/2018
Expiration:
Status:
ACKNOWLEDGED
Case Manager:
Mitch Moore
Phone:
971-375-5094
Email:
mitch.moore@puc.oregon.gov
Staff Contact:
JASON KLOTZ
Phone:
503-378-6667
Email:
jason.klotz@state.or.us
If you experience problems with the
above
'Email Service List' links,
please try one of these:
Service List Popup (semi-colon delimited)
Service List Popup (comma delimited)
General information about Tariff Filings.
ACTIONS
SERVICE LIST
SCHEDULE
Public Comments
Date/Time
Event
Description
1/1/2018
EFFECTIVE DATE/ STATUTORY DEADLINE
12/18/2017
PUBLIC MEETING
New Search