In the Matter of PORTLAND GENERAL ELECTRIC COMPANY, Application for Deferred Accounting of Certain Revenues Associated with the Boardman Power Plant 100 Percent Biomass Test Burn. Filed by Stefan Brown.
Filing Date:
12/30/2016
Order:
17-023
Order Signed:
1/24/2017
Email Service List (semi-colon delimited)
Email Service List (comma delimited)
If you experience problems with the
above
'Email Service List' links,
please try one of these:
Service List Popup (semi-colon delimited)
Service List Popup (comma delimited)
ACTIONS
SERVICE LIST
SCHEDULE
Public Comments
Sort By Date
Sort By Type
Date:
1/24/2017
Action:
ORDER
Order No:
17-023
Description
Order No. 17-021, signed by Michael Dougherty, Chief Operating Officer; DISPOSITION: STAFF'S RECOMMENDATION ADOPTED. Copies served on 1/24/17.
Date:
1/19/2017
Action:
STAFF REPORT
Description
Staff Report for the January 27, 2017 Public Meeting (Item No. CA16), filed by Judy Johnson.
Date:
12/30/2016
Action:
INITIAL (APPLICATION, COMPLAINT, PETITION)
Description
In the Matter of PORTLAND GENERAL ELECTRIC COMPANY, Application for Deferred Accounting of Certain Revenues Associated with the Boardman Power Plant 100 Percent Biomass Test Burn. Filed by Stefan Brown.