Docket No:  UM 2383 Docket Name:  PACIFICORP APPLICATION FOR PARTIAL WAIVER DRAFT RFP Submit Public Comment
Subject Company:  PACIFIC POWER    
         See also:  ON APPEAL   LEGAL HOLD
In the Matter of PACIFICORP, dba PACIFIC POWER, Application for Partial Waiver of OAR Chapter 860-089, Request to Engage Independent Evaluator, and Approval of 2025 Draft RFP [Expedited Request]. Filed by Joseph Dallas. Confidential saved to Agency...
Filing Date:  4/16/2025    Public Mtg: 9/3/2026   
Case Manager:  BENEDIKT SPRINGER Phone:  
Email:   benedikt.springer@puc.oregon.gov
Law Judge:  KATIE MAPES Phone:  
 
Email Service List (semi-colon delimited)      Email Service List (comma delimited)
  If you experience problems with the above 'Email Service List' links,
please try one of these:
Service List Popup (semi-colon delimited)     Service List Popup (comma delimited)

ACTIONSSERVICE LISTSCHEDULE Public Comments
Date/TimeEventDescription
11/3/2026 MISCELLANEOUS Phase 2: RFP Issuance (planned)
10/27/2026 PUBLIC MEETING Phase 2: Commission decision at a public meeting (Draft RFP and remaining waivers). Specific TBD.
10/20/2026 MISCELLANEOUS Phase 2: Staff Report Posted (Draft RFP and remaining waivers)
9/28/2026 3:00:00 PM COMMENTS/RESPONSES DUE Phase 2: Company Reply (Draft RFP and remaining waivers)
9/14/2026 3:00:00 PM COMMENTS/RESPONSES DUE Phase 2: Stakeholder Comments (Draft RFP and remaining waivers)
9/3/2026 9:30:00 AM PUBLIC MEETING Item No. RA3
 Location:  HEARING ROOM - PUC
201 HIGH ST SE , SALEM, OR
9/3/2026 PUBLIC MEETING Phase 2: Commission decision at a public meeting (IE appointment and workshop waiver)
8/27/2026 MISCELLANEOUS Phase 2: Staff Report posted (IE appointment and workshop waiver)
8/21/2026 MISCELLANEOUS Phase 2: Draft RFP and waiver requests filed
6/23/2026 9:30:00 AM PUBLIC MEETING Item No. RA1. Commission decision at a public meeting
 Location:  HEARING ROOM - PUC
201 HIGH ST SE , SALEM, OR
6/12/2026 COMMENTS/RESPONSES DUE PacifiCorp files response to comments
6/9/2026 HEARING FSL Commission Workshop. Sepcifics TBD.
6/8/2026 COMMENTS/RESPONSES DUE Staff and Parties file comments on Final Shortlist
5/29/2026 COMMENTS/RESPONSES DUE PacifiCorp may file request for acknowledgement of FSL and IE closing report.
5/21/2026 MISCELLANEOUS 10-day response time for information requests begins.
5/8/2026 MISCELLANEOUS PacifiCorp provides FSL sensitivity analysis & workpapers to IE and Staff.
4/1/2026 MISCELLANEOUS PacifiCorp issues raw price bid rankings
8/26/2025 PUBLIC MEETING Special Public Meeting.
 Location:  VIRTUAL
8/25/2025 3:00:00 PM COMMENTS/RESPONSES DUE Responses to Staff Report Due
8/22/2025 3:00:00 PM COMMENTS/RESPONSES DUE Stakeholder Comments and Staff Report Due
8/21/2025 3:00:00 PM COMMENTS/RESPONSES DUE PacifiCorp/Stakeholder Comments and Staff Report Due
8/12/2025 MISCELLANEOUS Independent Evaluator Report on SMM and Draft RFP due
7/24/2025 COMMENTS/RESPONSES DUE Utility Response to Comments due
7/7/2025 COMMENTS/RESPONSES DUE Staff/Stakeholder Comments on SMM and Draft RFP due
7/1/2025 STAFF WORKSHOP Stakeholder Workshop: PacifiCorp Q&A on Scoring and Modeling Methodology and Draft RFP. See July 1, 2025 Agenda for Zoom Link and Details.
5/27/2025 1:30:00 PM PUBLIC MEETING Item No. RA2
 Location:  ZOOM