| Date/Time | Event | Description |
|
| 4/1/2026 3:00:00 PM |
BRIEF DUE |
Green Solar Reply Brief due by 3pm. |
| 3/10/2026 3:00:00 PM |
BRIEF DUE |
PacifiCorp Response Brief due by 3pm. |
| 2/13/2026 3:00:00 PM |
BRIEF DUE |
Green Solar Opening Brief due by 3pm. |
| 1/28/2026 |
HEARING |
Evidentiary Hearing |
| 1/14/2026 3:00:00 PM |
CROSS EXAMINATION STATEMENT DUE |
Deadline for Cross-Examination Statements
Exhibits, and Positions Statements/Issues
List due by 3pm. |
| 1/14/2026 3:00:00 PM |
ISSUE STATEMENT DUE |
Deadline for Cross-Examination Statements
Exhibits, and Positions Statements/Issues
List |
| 12/19/2025 3:00:00 PM |
TESTIMONY/EXHIBITS DUE |
Green Solar Reply Testimony due by 3pm. |
| 11/21/2025 3:00:00 PM |
TESTIMONY/EXHIBITS DUE |
PacifiCorp Response Testimony due by 3pm. |
| 10/17/2025 3:00:00 PM |
TESTIMONY/EXHIBITS DUE |
Green Solar Opening Testimony due by 3pm.(see ruling served on 10 13 25), |
| 10/13/2025 3:00:00 PM |
COMMENTS/RESPONSES DUE |
PacifiCorp may respond to Green Solar motion by 3pm. |
| 9/17/2025 3:00:00 PM |
COMMENTS/RESPONSES DUE |
Green Solar Reply to PacifiCorp due by 3pm. |
| 9/10/2025 3:00:00 PM |
COMMENTS/RESPONSES DUE |
PacifiCorp Response to Green Solar Motion due by 3pm. |
| 8/21/2025 10:00:00 AM |
CONFERENCE |
Notice of Prehearing Conference to be held on 8 21 25. Copies served on 7 29 25. |
| 8/20/2025 3:00:00 PM |
MISCELLANEOUS |
Proposed schedule due by 3pm. |
| 7/31/2025 5:00:00 PM |
INTERNAL DEADLINE |
Prehearing Conference date selection due by 5pm. |
| 7/25/2025 3:00:00 PM |
ANSWER DUE |
PacifiCorp's answer to Green Solar's amended complaint due by 3pm. |
| 7/11/2025 3:00:00 PM |
OTHER FILING DUE |
Deadline to Amend Complaint or File Cross Complaint |
| 7/11/2025 3:00:00 PM |
MISCELLANEOUS |
Green Solar to determine whether it intends to amend its complaint or dismiss the complaint due by 3pm. See Ruling on 6-11-25 for update. |
| 7/11/2025 3:00:00 PM |
MISCELLANEOUS |
PacifiCorp to determine whether it intends to file a cross complaint due by 3pm. See Ruling on 6-11-25 for update. |
| 7/1/2025 3:00:00 PM |
COMMENTS/RESPONSES DUE |
Replies to Responses to Green Solar Motion |
| 6/26/2025 3:00:00 PM |
COMMENTS/RESPONSES DUE |
Responses to Green Solar Motion for Interim Relief |
| 6/16/2025 3:00:00 PM |
COMMENTS/RESPONSES DUE |
Green Solar to file any response to PacifiCorp's June 9, 2025 reply (See 6/11/25 Ruling) |
| 6/10/2025 2:00:00 PM |
CONFERENCE |
Notice of Procedural Conference. Copies served on 6-5-25. |
| 3/31/2025 3:00:00 PM |
MISCELLANEOUS |
Parties to file a status update by 3pm. |
| 1/31/2025 3:00:00 PM |
COMMENTS/RESPONSES DUE |
Parties file update re status of invoices and need to resume proceedings. |
| 6/28/2024 3:00:00 PM |
COMMENTS/RESPONSES DUE |
Green Solar letter re intentions to amend complaint or withdraw any remaining issues in original complaint due. |
| 6/7/2024 3:00:00 PM |
COMMENTS/RESPONSES DUE |
Parties' file status updates as each remaining milestone is completed, and an overall status update due no later than 6/7/24. |
| 5/15/2024 2:30:00 PM |
CONFERENCE |
NOTICE OF PREHEARING CONFERENCE. Copies served on 5/10/24. |
| | Location: VIA ZOOM |
| 5/9/2024 12:00:00 PM |
COMMENTS/RESPONSES DUE |
PacifiCorp files an update after interconnection or an update that provides its latest estimate for interconnection by noon on May 9, 2024. |
| 5/8/2024 3:00:00 PM |
COMMENTS/RESPONSES DUE |
Parties' Written Statements on Further Process due. |
| 5/3/2024 3:00:00 PM |
COMMENTS/RESPONSES DUE |
Green Solar Reply to any Affirmative Defenses Raised by PacifiCorp due. |
| 5/2/2024 2:00:00 PM |
CONFERENCE |
NOTICE OF PREHEARING CONFERENCE. Copies served on 4/25/24. |
| | Location: ZOOM |
| 4/26/2024 3:00:00 PM |
ANSWER DUE |
PacifiCorp's Answer due. |
| 4/18/2024 |
CONFERENCE |
Prehearing Conference - April 18, 2024 2:00 p.m. |