eFiling
Docket No:
ADV 1328
Docket Name:
PGE ADVICE NO. 21-28 SCHEDULE 145 BOARDMAN DECOMMISSIONING ADJUSTMENT
Submit Public Comment
Subject Company:
PORTLAND GENERAL ELECTRIC
PGE Advice No. 21-28, Schedule 145 Boardman Power Plant Decommissioning Adjustment. The purpose of Schedule 145 Boardman Power Plant Decommissioning Adjustment is to implement the revenue requirement effect of the decommissioning expenses related to the...
Filing Date:
10/26/2021
Advice No:
21-28
Public Mtg:
11/30/2021
Effective:
1/1/2022
Expiration:
Status:
ALLOWED
Case Manager:
MING PENG
Phone:
503-508-3040
Email:
ming.peng@puc.oregon.gov
Email Service List (semi-colon delimited)
Email Service List (comma delimited)
If you experience problems with the
above
'Email Service List' links,
please try one of these:
Service List Popup (semi-colon delimited)
Service List Popup (comma delimited)
ACTIONS
SERVICE LIST
SCHEDULE
Public Comments
Sort By Date
Sort By Type
Date:
11/30/2021
Action:
OTHER CORRESPONDENCE (ACKN, SVC, LTR)
Description
Proof of service of letter 11/30/2021.
Date:
11/30/2021
Action:
ALLOWED (APPROVED) UTILITY FILING
Description
Letter Sent
Date:
11/24/2021
Action:
STAFF REPORT
Description
Staff Report for the November 30, 2021 Public Meeting (Item No. CA9), by Ming Peng.
Date:
10/26/2021
Action:
INITIAL UTILITY FILING
Description
PGE Advice No. 21-28, Schedule 145 Boardman Power Plant Decommissioning Adjustment. The purpose of Schedule 145 Boardman Power Plant Decommissioning Adjustment is to implement the revenue requirement effect of the decommissioning expenses related to the Boardman Power Plant.