Sort By Date
Sort By Type
|
Date: |
8/16/2024 |
Action: COMMENTS/RESPONSE |
|
|
Description
NW Energy Coalition and CUB's Comments, filed by Alessandra de la Torre and Jennifer Hill-Hart. |
Date: |
8/15/2024 |
Action: OTHER FILING/PLEADING |
|
|
Description
UM 2340 - Staff's Docket Update and Workshop Notice |
Date: |
8/9/2024 |
Action: COMMENTS/RESPONSE |
|
|
Description
Idaho Power Company's Comments; filed by Alison Williams, Jon Axtman, and Dani Southard. |
Date: |
8/9/2024 |
Action: COMMENTS/RESPONSE |
|
|
Description
NW Energy Coalition’s and CUB’s Phase I comments; filed by Alessandra de la Torre and Jennifer Hill-Hart. |
Date: |
7/26/2024 |
Action: OTHER FILING/PLEADING |
|
|
Description
Staff's WMP Phase 1 Staff Proposal, filed by Heide Caswell. |
Date: |
7/23/2024 |
Action: OTHER FILING/PLEADING |
|
|
Description
Staff's WMP Advancement: Phase 1 Docket Announcement, filed by Heide Caswell. |
Date: |
7/10/2024 |
Action: ORDER |
|
|
Order No:
24-231 |
|
Description
Order No. 24-231, signed by Chief Administrative Law Judge Alison Lackey; DISPOSITION: STAFF'S RECOMMENDATION ADOPTED. Copies served on 7/10/24. |
Date: |
7/9/2024 |
Action: OTHER FILING/PLEADING |
|
|
Description
Staff's Presentation for the July 9, 2024 Public Meeting. |
Date: |
7/5/2024 |
Action: STAFF REPORT |
|
|
Description
Staff Report for the July 9, 2024 Public Meeting (Item No. RA2), by Heide Caswell. |
Date: |
7/2/2024 |
Action: COMMENTS/RESPONSE |
|
|
Description
CUB's Comments on Draft Staff WMP Reports, filed by Jennifer Hill-Hart. |
Date: |
7/1/2024 |
Action: COMMENTS/RESPONSE |
|
|
Description
Idaho Power Company's Final Comments, filed by Alison Williams. |
Date: |
6/24/2024 |
Action: OTHER FILING/PLEADING |
|
|
Description
Draft Staff Report for the July 9, 2024 Public Meeting. Filed by Natascha Smith. |
Date: |
6/12/2024 |
Action: OTHER FILING/PLEADING |
|
|
Description
Idaho Power Wildfire Mitigation Plan 2024 Independent Evaluator's Report. Filed by Natascha Smith. |
Date: |
6/6/2024 |
Action: OTHER FILING/PLEADING |
|
|
Description
Staff's Schedule Update, filed by Heide Caswell. |
Date: |
5/31/2024 |
Action: COMMENTS/RESPONSE |
|
|
Description
Idaho Power's Comments on IE Report. Filed by Alison Williams. |
Date: |
5/20/2024 |
Action: OTHER FILING/PLEADING |
|
|
Description
Independent Evaluator's DRAFT 2024 Report for Idaho Power's Wildfire Mitigation Plan. |
Date: |
5/10/2024 |
Action: OTHER FILING/PLEADING |
|
|
Description
Staff's Docket Announcement and Schedule |
Date: |
3/19/2024 |
Action: OTHER FILING/PLEADING |
|
|
Description
Staff's Presentation for the March 19, 2024 Special Public Meeting. |
Date: |
3/18/2024 |
Action: OTHER FILING/PLEADING |
|
|
Description
Idaho Power's Presentation for the March 19, 2024 Special Public Meeting |
Date: |
2/1/2024 |
Action: OTHER FILING/PLEADING |
|
|
Description
CUB's Request for Huddle Access, filed by Jennifer Hill-Hart. |
Date: |
2/1/2024 |
Action: NOTICE |
|
|
Description
CUB's Notice of Intervention, with contacts of Jennifer Hill-Hart, Bob Jenks, and CUB Oregon Dockets. Filed by Jennifer Hill-Hart. |
Date: |
12/29/2023 |
Action: SUPPLEMENTAL APPLICATION |
|
|
Description
UM 2209(2) - In the Matter of IDAHO POWER COMPANY, 2024 Wildfire Mitigation Plan. Filed by Alison Williams.
Copies served to Electric Service Lists. |
Date: |
6/26/2023 |
Action: ORDER |
|
|
Order No:
23-222 |
|
Description
Order No. 23-222, signed by Commissioners Megan W. Decker, Letha Tawney, and Mark R. Thompson; DISPOSITION: STAFF'S RECOMMENDATION ADOPTED AS MODIFIED. Copies served on 6/26/23 after 5:00 p.m. |
Date: |
6/8/2023 |
Action: COMMENTS/RESPONSE |
|
|
Description
Idaho Power Company's Comments, filed by Alison Williams. |
Date: |
6/6/2023 |
Action: STAFF REPORT |
|
|
Description
Staff Report for the June 13, 2023, Public Meeting (Item No. RA3), by Heidi Caswell. |
Date: |
6/5/2023 |
Action: OTHER FILING/PLEADING |
|
|
Description
UPDATED Independent Evaluator Report on Wildfire Mitigation Plan Compliance |
Date: |
5/31/2023 |
Action: COMMENTS/RESPONSE |
|
|
Description
STOP B2H Comments filed by Jim Kreider. |
Date: |
5/31/2023 |
Action: COMMENTS/RESPONSE |
|
|
Description
Idaho Power Company's Comments on Independent Evaluator's Report; filed by Alison Williams. |
Date: |
5/31/2023 |
Action: COMMENTS/RESPONSE |
|
|
Description
Sam Myers Comments. |
Date: |
5/31/2023 |
Action: COMMENTS/RESPONSE |
|
|
Description
Wendy King's Comments. |
Date: |
5/23/2023 |
Action: OTHER FILING/PLEADING |
|
|
Description
Independent Evaluator Report on Wildfire Mitigation Plan Compliance. |
Date: |
5/11/2023 |
Action: OTHER FILING/PLEADING |
|
|
Description
Staff's Comment Period Update |
Date: |
5/9/2023 |
Action: COMMENTS/RESPONSE |
|
|
Description
Joint Utilities Comments, filed by Alison Williams (Idaho Power), William Messner (PGE), and Amy McCluskey (PacifiCorp). |
Date: |
4/28/2023 |
Action: OTHER FILING/PLEADING |
|
|
Description
Staff's Workplan and Comment Period Notice |
Date: |
3/20/2023 |
Action: OTHER FILING/PLEADING |
|
|
Description
Staff's Presentation from the 3/14/23 Workshop |
Date: |
3/20/2023 |
Action: OTHER FILING/PLEADING |
|
|
Description
Idaho Power's Presentation from the 3/14/23 Workshop |
Date: |
2/27/2023 |
Action: NOTICE |
|
|
Description
Notice of Public Workshop for IOUs to Present 2023 WMPs
Copies served to AR 638 Service List. |
Date: |
2/3/2023 |
Action: COMMENTS/RESPONSE |
|
|
Description
STOP B2H's Withdrawal of Intervenor Funding Request. Filed by Jim Kreider. |
Date: |
1/17/2023 |
Action: LAW JUDGE RULING/MEMORANDA |
|
|
Description
Chief ALJ Nolan Moser issues Bench Request. Copies served on 1/17/23. |
Date: |
1/5/2023 |
Action: COMMENTS/RESPONSE |
|
|
Description
Stop B2H Coalition's Response to Idaho Power regarding their intervenor funding status, filed by Jim Kreider. |
Date: |
12/29/2022 |
Action: SUPPLEMENTAL APPLICATION |
|
|
Description
UM 2209(1) - Idaho Power Company's 2023 Wildfire Mitigation Plan; filed by Stacy Gust.
Sent to UM 2209 and Electric Service Lists. |
Date: |
12/28/2022 |
Action: COMMENTS/RESPONSE |
|
|
Description
Idaho Power's Response to STOP B2H's Request for Intervenor Funding, filed by Jocelyn Pease and Donovan. |
Date: |
12/19/2022 |
Action: COMMENTS/RESPONSE |
|
|
Description
UM 2211, UM 2210, UM 2209, AR 638, AR 626, PCN 5, and LC 78 - AWEC's Response to Coalition's Request for Intervenor Funding. Filed by Tyler Pepple. |
Date: |
12/13/2022 |
Action: LAW JUDGE RULING/MEMORANDA |
|
|
Description
UM 2211, UM 2210, UM 2209, AR 638, AR 626, PCN 5, LC 78: Chief ALJ Nolan Moser issues Memorandum: Responses to the STOP B2H Coalition's requests for intervenor funding due December 28, 2022, and replies from the STOP B2H Coalition due January 5, 2023. Copies served 12/13/2022. |
Date: |
12/12/2022 |
Action: OTHER FILING/PLEADING |
|
|
Description
STOP B2H Coalition's Request to be found eligible for Intervenor Funds, filed by Jim Kreider. |
Date: |
11/18/2022 |
Action: OTHER FILING/PLEADING |
|
|
Description
Idaho Power Company's Presentation Slides from the November 17, 2022 Workshop, filed by Stacy Gust. |
Date: |
11/7/2022 |
Action: NOTICE |
|
|
Description
Idaho Power's Notice of Workshop on Wildfire Mitigation Plan
November 17, 2022
9:00-11:00 am Pacific (10:00 am - noon Mountain)
|
Date: |
8/26/2022 |
Action: ORDER |
|
|
Order No:
22-312 |
Date: |
8/18/2022 |
Action: STAFF REPORT |
|
|
Description
Staff Report for the August 23, 2022 Public Meeting (Item No. CA7), by Yassir Rashid. |
Date: |
6/28/2022 |
Action: COMPLIANCE |
|
|
Description
Idaho Power Company's Wildfire Protection Plan, in compliance with Order No. 22-133; filed by Alison Williams. |
Date: |
4/28/2022 |
Action: ORDER |
|
|
Order No:
22-133 |
|
Description
Order No. 22-133, signed by Commissioners Megan W. Decker, Letha Tawney, and Mark R. Thompson; IDAHO POWER COMPANY'S WILDFIRE MITIGATION PLAN APPROVED. Copies served on 4/28/22. |
Date: |
4/19/2022 |
Action: STAFF REPORT |
|
|
Description
Staf Report for the April 21, 2022 Special Public Meeting (Item No. RA3), by Lori Koho, Yassir Rashid, and Lisa Gorsuch. |
Date: |
4/18/2022 |
Action: COMMENTS/RESPONSE |
|
|
Description
STOP B2H Coalition's Comments on Idaho Power Wildfire Protection Plan, filed by Jim Kreider. |
Date: |
4/18/2022 |
Action: STAFF REPORT |
|
|
Description
Staff Report for the April 21, 2022 Special Public Meeting, Item RA3, filed by Lori Koho, Yassir Rashid, and Lisa Gorsuch. Copies served 4/19/2022. |
Date: |
4/11/2022 |
Action: OTHER FILING/PLEADING |
|
|
Description
Staff Procedural/Schedule Change, filed by Lori Koho. |
Date: |
3/11/2022 |
Action: COMMENTS/RESPONSE |
|
|
Description
Idaho Power Company's Wildfire Protection Plan Comments on Independent Evaluator's Draft Report, filed by Alison Williams. |
Date: |
3/8/2022 |
Action: SERVICE LIST CHANGE |
|
|
Description
Staff Request to Change Service List, filed by Natascha Smith. |
Date: |
2/25/2022 |
Action: COMMENTS/RESPONSE |
|
|
Description
STOP B2H Coalition's Comments on Idaho Power's Wildlife Protection Plan. |
Date: |
2/24/2022 |
Action: OTHER FILING/PLEADING |
|
|
Description
Bureau Veritas draft evaluation of Idaho Power's WMOP, filed by Lori Koho. |
Date: |
1/31/2022 |
Action: OTHER FILING/PLEADING |
|
|
Description
BV Expectation of Demonstrated Compliance |
Date: |
1/26/2022 |
Action: OTHER FILING/PLEADING |
|
|
Description
AR 648, UM 2207, 2208, 2209 - Workshop Announcement - Evaluation of Wildfire Mitigation Plans. Filed by Lori Koho. |
Date: |
1/19/2022 |
Action: OTHER FILING/PLEADING |
|
|
Description
AR 648, UM 2207, UM 2208, UM 2209 - Agenda for Evaluation Workshop I - 01-19-2022 filed by Lori Koho.) |
Date: |
1/13/2022 |
Action: LAW JUDGE RULING/MEMORANDA |
|
|
Description
Chief ALJ Nolan Moser issues Ruling; DISPOSITION: SCHEDULE ADOPTED. Copies served on 1/13/22. |
Date: |
1/10/2022 |
Action: MOTION |
|
|
Description
Staff's Stipulated Motion to Adopt Procedural Schedule [Expedited Consideration Requested], filed by Sommer Moser. |
Date: |
12/30/2021 |
Action: INITIAL (APPLICATION, COMPLAINT, PETITION) |
|
|
Description
In the Matter of IDAHO POWER COMPANY, Wildfire Protection Plan.
Sent to Electric, AR 938, AR 648 Service Lists. |
Date: |
12/10/2021 |
Action: CONFERENCE |
|
|
Description
NOTICE OF SCHEDULING CONFERENCE. Copies served to UM 2207, UM 2208, UM 2209, AR 638, AR 648, and Electric Service Lists on 12/10/21.
CONFERENCE scheduled 12/21/2021 10:00 AM
Room: VIA ZOOM
Reporter: ZOOM RECORDING
Law Judge: MOSER, NOLAN
|