Date/Time | Event | Description |
|
6/1/2025 |
EFFECTIVE DATE/ STATUTORY DEADLINE |
Effective Date |
5/27/2025 |
FINAL ORDER DUE DATE |
Target Order Date |
5/6/2025 3:00:00 PM |
SETTLEMENT PROPOSAL DUE |
Settlement Due by 3pm. |
4/30/2025 |
SETTLEMENT CONFERENCE |
Settlement Conference specifics TBD. |
4/23/2025 3:00:00 PM |
TESTIMONY/EXHIBITS DUE |
All Parties Reply Testimony due by 3pm. |
4/16/2025 |
SETTLEMENT CONFERENCE |
Settlement Conference specifics TBD. |
4/14/2025 3:00:00 PM |
TESTIMONY/EXHIBITS DUE |
Staff and Intervenor Testimony on March Forecast due by 3pm.(see ruling dated 4-3-25). |
4/9/2025 |
SETTLEMENT CONFERENCE |
Settlement Conference specifics TBD.(see ruling dated 4-3-25) |
3/24/2025 3:00:00 PM |
MISCELLANEOUS |
Idaho Power's March Forecast due by 3pm. |
2/26/2025 3:00:00 PM |
TESTIMONY/EXHIBITS DUE |
Company Reply Testimony due by 3pm. |
2/12/2025 |
SETTLEMENT CONFERENCE |
Settlement Conference specifics TBD. |
1/29/2025 3:00:00 PM |
TESTIMONY/EXHIBITS DUE |
Staff and Intervenor Opening Testimony due by 3pm. |
1/8/2025 |
SETTLEMENT CONFERENCE |
Settlement Conference specifics TBD. |
11/20/2024 3:00:00 PM |
MISCELLANEOUS |
Parties to Filed Schedule(s) |