Sort By Date
Sort By Type
|
Date: |
5/2/2024 |
Action: ORDER |
|
|
Order No:
24-116 |
|
Description
UM 2078(3) - Order No. 24-116, signed by Chief Administrative Law Judge Nolan Moser; DISPOSITION: STAFF'S RECOMMENDATION ADOPTED. Copies served on 5/2/24. |
Date: |
4/24/2024 |
Action: STAFF REPORT |
|
|
Description
Staff Report for the April 30, 2024 Public Meeting, Item No. CA 6, filed by Kathy Zarate. |
Date: |
4/19/2024 |
Action: SUPPLEMENTAL APPLICATION |
|
|
Description
UM 2078(4) - In the Matter of PORTLAND GENERAL ELECTRIC COMPANY, Application for Reauthorization to Defer Costs Associated with the Residential Battery Energy Storage Pilot. Filed by Jaki Ferchland.
Sent to the Electric List. |
Date: |
10/27/2023 |
Action: SERVICE LIST CHANGE |
|
|
Description
CUB’s request to change the service list by removing William Gehrke; filed by Sharif Morton. |
Date: |
4/24/2023 |
Action: SUPPLEMENTAL APPLICATION |
|
|
Description
UM 2078(3) - In the Matter of PORTLAND GENERAL ELECTRIC COMPANY, Application for Reauthorization to Defer Costs Associated with the Residential Battery Energy Storage Pilot. Filed by Jaki Ferchland.
Sent to the Electric List. |
Date: |
6/2/2022 |
Action: ORDER |
|
|
Order No:
22-201 |
|
Description
Order No. 22-201 signed by Chief Administrative Law Judge Nolan Moser; DISPOSITION: STAFF'S RECOMMENDATION ADOPTED.
Copies served 6/3/22 |
Date: |
5/26/2022 |
Action: STAFF REPORT |
|
|
Description
Staff Report for the May 31, 2022 Public Meeting (Item No. CA7); filed by Heide Caswell. |
Date: |
4/20/2022 |
Action: SUPPLEMENTAL APPLICATION |
|
|
Description
UM 2078(2) PORTLAND GENERAL ELECTRIC COMPANY, Application for Reauthorization to Defer Costs Associated with the Residential Battery Energy Storage Pilot.
Sent to the electric list. |
Date: |
6/9/2021 |
Action: SERVICE LIST CHANGE |
|
|
Description
PGE Notice of Change to Service List, removing Douglas Tingey and adding Loretta I. Mabinton, filed by Loretta I. Mabinton. |
Date: |
5/18/2021 |
Action: ORDER |
|
|
Order No:
21-156 |
|
Description
UM 2078(1) Order No. 21-156 signed by Chief Administrative Law Judge Nolan Moser; DISPOSITION: STAFF'S RECOMMENDATION ADOPTED.
Copies served 5/18/2021 |
Date: |
5/12/2021 |
Action: STAFF REPORT |
|
|
Description
UM 2078(1) - Staff Report for the May 18, 2021 Public Meeting (Item No. CA6), by Mitchell Moore. |
Date: |
4/12/2021 |
Action: SUPPLEMENTAL APPLICATION |
|
|
Description
UM 2078(1) PGE Application for Deferral Reauthorization of Deferred Accounting Costs.
Sent to Electric List. |
Date: |
7/6/2020 |
Action: ORDER |
|
|
Order No:
20-208 |
|
Description
Order No. 20-208, signed by Nolan Moser, Chief Administrative Law Judge; DISPOSITION: STAFF'S RECOMMENDATION ADOPTED. Copies served on 7/6/20. |
Date: |
6/25/2020 |
Action: STAFF REPORT |
|
|
Description
Staff Report for the June 30, 2020 Public Meeting (Item No. CA1), by Mitchell Moore and Nicholas Colombo. |
Date: |
4/28/2020 |
Action: OTHER FILING/PLEADING |
|
|
Description
CUB's Request for Huddle Access, filed by Michael Goetz. |
Date: |
4/28/2020 |
Action: NOTICE |
|
|
Description
CUB's Notice of Intervention, with contacts of Michael Goetz, William Gehrke, and Oregon CUB Dockets. Filed by Michael Goetz. |
Date: |
4/21/2020 |
Action: INITIAL (APPLICATION, COMPLAINT, PETITION) |
|
|
Description
In the Matter of PORTLAND GENERAL ELECTRIC COMPANY, Application for Deferral of Costs Associated with the Residential Battery Energy Storage Pilot. Filed by Jaki Ferchland.
Sent to Electric List. |