Docket No:  UE 321 Docket Name:  IDAHO POWER AMORTIZATION REVENUE LANGLEY GULCH/INTERVENOR FUNDING Submit Public Comment
Subject Company:  IDAHO POWER COMPANY    
In the Matter of IDAHO POWER COMPANY, Request for Amortization of Certain Expenses Relating to the Revenue Requirement Variances with the Langley Gulch Power Plant and Intervenor Funding, filed by Lisa Nordstrom.
Filing Date:  2/28/2017 Advice No: 17-03    Public Mtg: 5/30/2017   
Effective:  6/1/2017 Expiration:   Status:  ACKNOWLEDGED
Order:  17-198Order Signed:  5/30/2017 
Email Service List (semi-colon delimited)      Email Service List (comma delimited)
  If you experience problems with the above 'Email Service List' links,
please try one of these:
Service List Popup (semi-colon delimited)     Service List Popup (comma delimited)

ACTIONSSERVICE LISTSCHEDULE Public Comments
Sort By Date        Sort By Type
Date: 6/3/2017 Action:  ACKNOWLEDGED UTILITY FILING  Searchable Doc  
  Description
Letter emailed 
Date: 6/1/2017 Action:  REPLACEMENT SHEETS, ADDITIONAL MATERIAL  Searchable Doc  
  Description
Idaho Power's Third Supplement to Tariff Advice No. 17-03 - Schedule 56, Power Cast Adjustment Mechanism.  
Date: 5/30/2017 Action:  ORDER  Getdocs  
  Order No:   17-198 
  Description
Order no. 17-198, signed by Michael Dougherty, Chief Operating Officer; DISPOSITION: STAFF'S RECOMMENDATION ADOPTED. Copies served on 6/1/17.  
Date: 5/24/2017 Action:  STAFF REPORT  Searchable Doc  
  Description
Staff Report for the May 30, 2017 Public Meeting (Item No. CA4), filed by Rose Anderson.  
Date: 4/28/2017 Action:  REPLACEMENT SHEETS, ADDITIONAL MATERIAL  Searchable Doc  
  Description
Idaho Power's SECOND SUPPLEMENT to Tariff Advice No. 17-03 - Schedule 56 -- Regarding Intervenor Funding 
Date: 4/25/2017 Action:  STAFF REPORT  Searchable Doc  
  Description
Letter emailed 
Date: 3/21/2017 Action:  ORDER  Getdocs  
  Order No:   17-120 
  Description
Order No. 17-120, signed by Commissioners Lisa D. Hardie and John Savage; DISPOSITION: STAFF'S RECOMMENDATION ADOPTED. Copies served 3/22/17. 
Date: 3/20/2017 Action:  SERVICE LIST CHANGE  Searchable Doc  
  Description
IDAHO POWER's Request to Change the Service List, removing Matt Larkin and adding Lisa Rackner. Filed by Wendy McIndoo.  
Date: 3/16/2017 Action:  STAFF REPORT  Searchable Doc  
  Description
Staff Report for the March 21, 2017 Public Meeting (Item No. 1), filed by Rose Anderson.  
Date: 3/15/2017 Action:  REPLACEMENT SHEETS, ADDITIONAL MATERIAL  Searchable Doc  
  Description
Idaho Power's Supplement to Tariff Advice No. 17-03 - Schedule 56. This filing adds clarifying language and sets rates to Schedule 56 to zero for all customer classes except residential service customers when collection of the deferred power cost amounts currently in amortization would be complete. This filing includes a Less Than Statutory Notice Application (LSN).  
Date: 3/10/2017 Action:  TESTIMONY & EXHIBITS  Searchable Doc  
  Description
IDAHO POWER's Errata Exhibit 105 to Direct Testimony of Courtney Waites (Idaho Power/105, Waites), filed by Lisa Nordstrom.  
Date: 2/28/2017 Action:  INITIAL UTILITY FILING  Searchable Doc  
  Description
IDAHO POWER's Advice No. 17-03, Schedule 56. This tariff is being filed in conjunction with Request for Amortization of Certain Expenses Relating to the Revenue Requirement Variances with the Langley Gulch Power Plant and Intervenor Funding.  
Date: 2/28/2017 Action:  TESTIMONY & EXHIBITS  Searchable Doc  
  Description
IDAHO POWER's Direct Testimony and Exhibits of Courtney Waites (Idaho Power/100-105, Waites), filed by Lisa Nordstrom. (See errata filed 3/10/17). 
Date: 2/28/2017 Action:  INITIAL (APPLICATION, COMPLAINT, PETITION)  Searchable Doc  
  Description
In the Matter of IDAHO POWER COMPANY, Request for Amortization of Certain Expenses Relating to the Revenue Requirement Variances with the Langley Gulch Power Plant and Intervenor Funding, filed by Lisa Nordstrom.