ORDER NO. 97-451
ENTERED NOV 24 1997
This is an electronic copy.
BEFORE THE PUBLIC UTILITY COMMISSION
OF OREGON
UE 101
In the Matter of Portland General Electric Companys Customer Choice Pilot Program. | ) ) ) |
|
DISPOSITION: DOCKET CLOSED
On August 1, 1997, Portland General Electric Company (PGE) filed rate schedules in Advice No. 97-13 to be effective October 1, 1997. On September 18, 1997, PGE filed modifications of the rate schedules. The Commission suspended the rate schedules in Order No. 97-383 issued September 30, 1997.
On October 8, 1997, PGE withdrew all the suspended tariff sheets and filed revised and additional sheets to be effective October 22, 1997. It also filed an Application to Waive Statutory Notice. It also requested that the Commission approve certain other provisions of its Customer Choice Program.
The Commission considered this matter at its public meeting on October 21, 1997. Staff filed a report recommending that the Commission allow the revised and new sheets to become effective on less than statutory notice and approve the other requests made by PGE. The Commission adopted Staffs recommendation.
CONCLUSIONS
The Commission concludes that there is no reason to keep this docket open. Any matters relating to these tariffs or to PGEs Pilot Program that come before us in the future will be treated in new dockets.
ORDER
IT IS ORDERED that docket UE 101 is closed
Made, entered, and effective ____________________________.
______________________________ |
______________________________ |
______________________________ |
A party may request rehearing or reconsideration of this order pursuant to ORS 756.561. A request for rehearing or reconsideration must be filed with the Commission within 60 days of the date of service of this order. The request must comply with the requirements of OAR 860-014-0095. A copy of any such request must also be served on each party to the proceeding as provided by OAR 860-013-0070. A party may appeal this order to a court pursuant to ORS 756.580.