ORDER NO. 97-157

ENTERED APR 24 1997

This is an electronic copy.

BEFORE THE PUBLIC UTILITY COMMISSION

OF OREGON

UT 139

In the Matter of the Investigation into the Compliance Tariffs filed by GTE Northwest Incorporated, Advice No. 589 ) ORDER

)

DISPOSITION: ADVICE NO. 589 AUTHORIZED TO TAKE EFFECT

SUBJECT TO REFUND; DOCKET UT 139 OPENED

On November 1, 1996, the Oregon Public Utility Commission (Commission) issued Order No. 96-283 in docket UM 351. In that order, the Commission required GTE Northwest Incorporated (GTE) to file tariffs for unbundled building blocks at the rates specified in Revised Appendix C. On December 16, 1996, GTE filed Advice No. 589 in response to Order No. 96-283.

At its January 21, 1997, public meeting, the Commission granted GTE additional time to engage in discussions with the Commission Staff (Staff) and telecommunications carriers likely to purchase building blocks from GTE’s tariff, and to make revisions to its filing. The Commission ordered GTE to refile its compliance tariffs on March 14, 1997, with an effective date of April 2, 1997. On March 14, 1997, GTE filed a supplement to Advice No. 589, which completely replaced the earlier version.

At its April 1, 1997, public meeting, the Commission considered recommendations from Staff and other interested persons regarding Advice No. 589. Staff proposed that Advice No. 589 be suspended for investigation. Other parties suggested that the tariffs be placed into effect subject to refund. The Commission decided to postpone decision on the matter until the April 15, 1997, public meeting, pending further review.

At its April 15, 1997, public meeting, the Commission approved a Staff recommendation to allow the tariffs in Advice No. 589 to go into effect subject to refund pursuant to ORS 759.185. The Commission also initiated this proceeding, designated as docket UT 139, to investigate the reasonableness of the tariff provisions in Advice No. 589.

The investigation in this docket shall be limited to consideration of nonrecurring charges, special construction charges, tariff terms and conditions proposed by GTE in Advice No. 589, and other matters necessary to ensure compliance with Order Nos. 96-188 and 96-283 in docket UM 351. Building block prices shall not be considered in this docket. Any refunds authorized by the Commission at the conclusion of this investigation shall include interest accrued at GTE’s authorized rate of return.

GTE shall keep records of demand for each building block by customer until the Commission has concluded its investigation and refunds are calculated.

Made, entered, and effective ________________________. 

______________________________

Roger Hamilton

Chairman

____________________________

Ron Eachus

Commissioner

  ____________________________

Joan H. Smith

Commissioner