ORDER NO. 96-335

ENTERED DEC 30 1996

This is an electronic copy. Appendices may not be included.

BEFORE THE PUBLIC UTILITY COMMISSION

OF OREGON

UM 829

In the Matter of Safety Violation Citations

Issued to CENTRAL LINCOLN PUD (CLPUD)for Failure to Adequately Inspect and Repair NESC Violations in CLPUD Substations.

)
)
)
)
)

ORDER

DISPOSITION: COMPLIANCE ORDERED

At the December 17, 1996, Commission public meeting, Staff presented the attached November 25, 1996, report summarizing its findings and making recommendations to ensure future compliance with electrical code requirements. The report also includes a time schedule for compliance and recommended action should compliance not occur. The actions recommended by staff appear as Appendix A and are incorporated into this order by reference.

ORDER

IT IS ORDERED that Central Lincoln PUD shall comply with all the terms and conditions set forth in Appendix A.

Made, entered and effective ________________________________.


_________________________

Joan H. Smith

Chairman


___________________________

Ron Eachus

Commissioner

 
___________________________

Roger Hamilton

Commissioner

A party may request rehearing or reconsideration of this order pursuant to ORS 756.561. A request for rehearing or reconsideration must be filed with the Commission within 60 days of the date of this order. The request must comply with the requirements of OAR 860-14-095. A copy of any such request must also be served on each party to the proceeding as provided by OAR 860-13-070(2)(a). A party may appeal this order to a court pursuant to ORS 756.580.